  • Test plant, Norrköping (2013)
  • Chemical factory, Karlstad (2016)
  • WWTP, Norrköping, 50 kW ORC (2017)
  • Heating plant, Ronneby, 50 kW ORC (2017)
  • CHP for greenhouse, Katrineholm, 50 kW ORC (2017)
  • Heating plant, Hörby, 50 kW ORC (2018)
  • Heating plant, Örkelljunga, 250 kW ORC (2018)
  • Heating plant, Töreboda, 50 kW ORC (2019)
  • Heating plant, Moheda, 50 kW ORC (2019)
  • Landfill, Norrköping, 120 kW ORC  (2019)
  • Heating plant, Högsby, 50 kW ORC (2019)
  • Waste incinerator, Elverum, 0.5 MW ORC (2019)
  • Heating plant, Perstorp, 315 kW (2020)
  • Heating plant, Vilhelmina, 250 kW (2020)
  • Heating plant, Svenljunga, 315 kW ORC (2020)
  • Heating plant, Ystad 1, 250 kW ORC (2020)
  • Waste incinerator, Finspång, 0.5 MW (2020)
  • Heating plant, Ystad 2, 250 kW ORC (2021)
  • Heating plant, Ystad 3, 250 kW ORC (2021)
  • Heating plant, Gamleby, 90 kW ORC (2021)
  • Heating plant, Gislaved , 200 kW ORC (2021)
  • Waste incinerator, Nuuk, 355 kW ORC (2021)
  • Heating plant, Flen, 100 kW ORC (2021)
  • Heating plant, Tomelilla, 100 kW ORC (2021)
  • Heating plant, Tibro, 100 kW ORC (2022)
  • Heating plant, Emmaboda, 100 kW (2022)
  • Heating plant, Karlskrona, 355 kW (2022)
  • Waste incinerator, Tallinn, 110 kW (2022)